B4Restart PPA

Microsoft – Constellation Crane restart PPA

Announced Sep 20, 2024 Christopher M. Crane Clean Energy CenterLast verified Aug 3, 2026

Contractual weight

B4 evidence

The parties signed a 20-year PPA, Constellation began physical restoration work, PJM approved the interconnection request, and NRC restart reviews are active.

A signed PPA underwrites the restart. The plant remains in NRC review and is not yet operating.

Capacity

Capacity

MW firm
835 MW
MW optioned
Not disclosed

Record history

Status timeline

  1. Sep 20, 2024

    Deal announced

  2. Upgraded

    Aug 7, 2025

    Target restart advanced from 2028 to 2027.

  3. Upgraded

    Jun 3, 2026

    NRC issued a draft environmental assessment and finding of no significant impact.