Meta – Vistra PJM nuclear PPAs and uprates

Announced Jan 9, 2026 Perry, Davis-Besse, and Beaver Valley nuclear plantsLast verified Aug 3, 2026

Contractual weight

B3 evidence

Vistra entered 20-year PPAs with Meta for operating plant output and 433 MW of contracted uprates, with purchases scheduled to begin in late 2026.

The tracker records 2,600 MW, the disclosed floor for a total described as more than 2,600 MW. The 433 MW uprate is included, not added again.

Capacity

Capacity

MW firm
2,600 MW
MW optioned
Not disclosed

Record history

Status timeline

  1. Jan 9, 2026

    Deal announced